Finishing Plan with Failure

Not all plans are finished with success.

A task can be finished with Failed status which doesn’t fail a whole plan.

If a plan Manager decides to close a plan where any task is failed, cannot be workarounded and prevents successive tasks to be started, the whole plan can be closed with Failed status through Context menu.

Failed status closes tasks and enables audit log.